
Bank Holiday Weekend Works at Euston Station
As part Euston HS2 Enabling Project on behalf of Skanska this weekend Lowery Ltd successfully commissioned a new 11kV/415V Transformer Ring Main Unit (RMU), Diverted 1 Pilot cable and diverted two HV 11kV cables at various locations around Euston Station this bank holiday weekend.

Cable Fire Remediation at Euston
Following a lineside fire just outside Euston Station Lowery carried out the emergency of repair of 4 feeders enabling the re-energisation of Euston Station.

Network Rail Thanks Lowery for Works at Euston
Network Rail thanks Lowery for completing the emergency repair of 4 feeders enabling the re-energisation of Euston Station following a lineside fire.

Week 51 Sunningdale - Stage 3 commissioning
Successful completion. Works consisted of: o Split of the existing F2236 33kV feeder between Ascot and Knowle to F2082 and F2083 o Full RTU SCADA commissioning including all the alarms associated with the HV Switchgear and modules o HV protection (Line Differential Protection - Translay) o Commissioning of two new Auxiliary Transformers 33kV/415V

Week 50 – Sunningdale Stage 2
Successful completion of full SCADA pre-commissioning (end to end test) and new communication unit back to control room